Replaced sanitary sewer mainline pipes and
manholes from Grove Street to Maclean Court
·
Replaced sanitary sewer services to individual
homes
·
Made final water main connection at Hutchings
and Grove
·
Completed storm sewer installation
·
Abandoned old water valves and fire hydrants.
Work Anticipated to be completed Next week, May 16th to May 20th
·
Begin roadway excavation and installation of
aggregate base course
·
Concrete curb & gutter installation
By the end of the week, the majority of the underground
utility improvements should be completed with only a few minor items remaining.
The project will be moving into the roadway reconstruction phase next week.
During the roadway reconstruction phase, the existing
roadway will be excavated approximately 12-inches deep with new aggregate base
course installed prior to installing new concrete curb & gutter and asphalt
pavement. During this time, it will be increasingly more difficult to drive
along the roadway during working hours because the entire roadway width will be
excavated at the same time. Access will be granted to driveways each evening.
We are requesting you do not park along the Hutchings Avenue during working
hours and move vehicles to side streets if they are needed during the day.
Once the roadway is excavated and new aggregate base course
is installed, new concrete curb & gutter will be installed. Additional
details will be provided regarding the schedule of this work, allowable
parking, and restrictions to driveway access. Access to driveways will be
restricted for approximately 1 week during the concrete curb & gutter
pouring and curing process.
Thank you again for all your patience and understanding as
the project moves into the roadway reconstruction phase which presents new
inconveniences as the process continues.