Grading of area disturbed during construction
·
Installation and final grading of topsoil
·
Sod Installation
·
Adjusting structures to final grade
·
Performed final testing for underground
utilities
·
Performed walk-through with Village staff to
find any items that need additional work
·
Made minor repairs at locations identified by
Village staff
·
General site clean-up
Work Anticipated to be completed Next week, July 18th
to July 22nd
·
Asphalt surface paving
·
Milling asphalt surface at intersection of Grove
Street and Hutchings Avenue
·
Milling asphalt surface at intersection of
MacLean Court and Hutching Avenue
·
Repair damaged sidewalk at Grove Street and
Hutchings Street
Paving of the asphalt surface
layer is scheduled for next week. Additional information will be provided when
the schedule is finalized regarding travel cautions and restrictions during the
paving operations and prior when the existing asphalt will have a thin layer of
oil sprayed on it.
The contractor has completed
the landscape restoration with sod. The contractor will continue to water the
sod until a healthy stand of grass is established.
The project is nearly
completed with only the asphalt surface paving and a few other minor items of
work to perform. Now that the sod is completed, hopefully you feel your yards
are back to the way they were prior to the project starting.
Thanks again for all your
patience, understanding, and cooperation during this long construction season.